VIRGINIA DCR STORMWATER
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
SECTION 1: DESCRIPTION Individual bioretention areas can serve highly impervious drainage areas less than two (2) acres in size. Surface runoff is directed into a shallow landscaped depression that incorporates many of the pollutant removal mechanisms that operate in forested ecosystems. The primary component of a bioretention practice is the filter bed, which has a mixture of sand, soil, and organic material as the filtering media with a surface mulch layer. During storms, runoff temporarily ponds 6 to 12 inches above the mulch layer and then rapidly filters through the bed. Normally, the filtered runoff is collected in an underdrain and returned to the storm drain system. The underdrain consists of a perforated pipe in a gravel layer installed along the bottom of the filter bed. A bioretention facility with an underdrain system is commonly referred to as a Bioretention Filter. Bioretention can also be designed to infiltrate runoff into native soils. This can be done at sites with permeable soils, a low groundwater table, and a low risk of groundwater contamination. This design features the use of a “partial exfiltration” system that promotes greater groundwater recharge. Underdrains are only installed beneath a portion of the filter bed, above a stone “sump” layer, or eliminated altogether, thereby increasing stormwater infiltration. A bioretention facility without an underdrain system, or with a storage sump in the bottom is commonly referred to as a Bioretention Basin. Small scale or Micro-Bioretention used on an individual residential lot is commonly referred to as a “Rain Garden.”. Bioretention creates a good environment for runoff reduction, filtration, biological uptake, and microbial activity, and provides high pollutant removal. Bioretention can become an attractive landscaping feature with high amenity value and community acceptance. The overall stormwater functions of the bioretention are summarized in Table 1.
SECTION 2: LEVEL 1 AND 2 DESIGN TABLES The most important design factor to consider when applying bioretention to development sites is the scale at which it will be applied: micro-bioretention or bioretention basins:
The major design goal for bioretention is to maximize nutrient removal and runoff reduction. To this end, designers may choose to go with the baseline design (Level 1) or choose an enhanced Level 2 design that maximizes nutrient and runoff reduction. If soil conditions require an underdrain, bioretention areas can still qualify for the Level 2 design if they contain a stone storage layer underneath the invert of the underdrain. Both stormwater quality and quantity credit are accounted for in the Runoff Reduction Method (RRM) design spreadsheet. The quality credit represents an annual load reduction as a combination of the annual reduction of runoff volume (40%, 80%, Level 1 and Level 2 respectively) and the reduction in the pollutant event mean concentration (EMC) (25% and 50%, Level 1 & 2). For computing the quantity reduction for larger storm events, the designer can similarly use the RRM Design Spreadsheet, or as an option, the designer may choose to compute the adjusted curve number associated with the retention storage using the TR-55 Runoff Equations as noted in Table 1. The adjusted curve number is then used to compute the peak discharge for the required design storms. Tables 2 and 3 outline the Level 1 and 2 design guidelines for the two scales of bioretention design.
SECTION 3: TYPICAL DETAILS Figures 1 through 4 provide some typical details for several bioretention configurations.
Figure 1: Typical Detail - Micro-Bioretention or Raingardens
Figure 2: Typical Detail – Bioretention Basin Level 1 & Level 2
Figure 3: Typical Detail - Bioretention with Additional Surface Ponding
Figure 4: Typical Detail - Bioretention Basin within the Upper Shelf of ED Pond SECTION 4: PHYSICAL FEASIBILITY & DESIGN APPLICATIONS Bioretention can be applied in most soils or topography since runoff simply percolates through an engineered soil bed and is returned to the stormwater system. Key constraints with bioretention include the following: Bioretention can be used wherever water can be conveyed to a surface area. Bioretention has been used at commercial, institutional, and residential sites in spaces that are traditionally pervious and landscaped. It should be noted that special care must be taken to provide adequate pre-treatment within the bioretention cell in space constrained high traffic areas. Typical locations for bioretention include the following: SECTION 5: DESIGN CRITERIA 5.1. Sizing of Bioretention Practices Stormwater Quality Sizing of the surface area (SA) for bioretention practices is based on the computed treatment volume (Tv) of the contributing drainage area and the storage provided in the facility. The required surface area, in square feet, is computed as the treatment volume in cubic feet divided by the equivalent storage depth in feet. The equivalent storage depth is computed as the depth of media, gravel, or surface ponding (in feet) multiplied by the accepted void ratio. The accepted Void Ratios (Vr) are (see Figure 5): Bioretention Soil Media Vr = 0.25 The equivalent storage depth for Level 1 with a 6” surface ponding depth is therefore computed as
And the equivalent storage depth for Level 2 with a 6” storage depth is computed as:
Figure 5: Typical Section with Void Ratios for Volume Computations Therefore, the Level 1 Bioretention Surface Area (SA) is computed as: (3) SA (ft2) = {Tv – volume reduced by upstream BMP} / 1.40 ft And the Level 2 Bioretention SA is computed as: (4) SA (ft2) = {(1.25 * Tv) – volume reduced by upstream BMP} / 1.65 ft Where: The effective storage depths will vary according to the actual design depths of the soil media and gravel layer. Stormwater Quantity In order to accommodate a greater quantity credit for channel and/or flood protection, designers may be able to create additional surface storage by expanding the surface ponding footprint without necessarily increasing the soil media footprint. In other words, the engineered soil media would only underlay part of the surface area of the bioretention (See Typical Details-Figure 3). In this regard, the ponding footprint can be increased as follows to allow for additional storage: These values may be modified as data on the long term permeability of bioretention filters becomes available. 5.2. Soil Infiltration Rate Testing In order to determine if an underdrain will be needed, one must measure the infiltration rate of subsoils at the invert elevation of the bioretention area as noted in the soil testing requirements for each scale of bioretention Design Tables 2 and 3.The infiltration rate of subsoils must exceed 1.0 inch per hour in order to dispense with the underdrain requirement for raingardens, and 0.5 inch/hour for bioretention basins. On-site soil infiltration rate testing procedures are outlined in Appendix A of the Infiltration Design Specification No. 8. Soil testing is not needed for Level 1 bioretention areas where an underdrain is used. 5.3. BMP Geometry Bioretention basins must be designed with an internal flow path geometry such that the treatment mechanisms provided by the bioretention are not by-passed or short-circuited. Examples of short-circuiting include inlets or curb cuts that are very close to outlet structures, or incoming flow that is diverted immediately to the underdrain through stone layers. Short-circuiting can be particularly problematic when there are multiple curb cuts or inlets. In order for these bioretention areas to have an acceptable internal geometry, the “travel time” from each inlet to the outlet should be maximized, and incoming flow must be distributed as evenly as possible across the filter surface area. One important characteristic is the length of the shortest flow path compared to the overall length, as shown in Figure 6. In the figure, ratio of the shortest flow path to the overall length is represented as: (5) SFP/L, where: SFP = length of the shortest flow path For Level 1 designs, the SFP/L ratio must be 0.3 or greater, and the ratio must be 0.8 or greater for Level 2. In some cases, due to site geometry, some inlets may not be able to meet these ratios; however, the drainage area served by these inlets should constitute no more than 20% of the contributing drainage area. Alternately, the designer may incorporate other design features that prevent short-circuiting, including features that help spread and distribute runoff as evenly as possible across the filter surface. Local reviewers may waive or modify the shortest flow path ratio guideline in cases where: With regard to #1 above, field experience has shown that soil media immediately around a raised outlet structure is prone to scouring and erosion, and thus short-circuiting of the treatment mechanism (water can flow straight down through scour holes or sinkholes to the underdrain system) (Hirschman et al., 2009). Design options should be used to prevent this type of scouring. One example is shown in Figure 7. The designer should ensure that incoming flow is spread as evenly as possible across the filter surface to maximize the treatment potential.
Figure 6. Diagram showing shortest flow path as part of BMP geometry.
Figure 7. Typical Detail – Preventing by-pass or short-circuiting around the overflow structure 5.4. Pretreatment Pretreatment of runoff entering bioretention areas is required to trap coarse sediment particles before they reach the filter bed, which prevents premature clogging. Pretreatment measures shall be designed to evenly spread runoff across the entire width of the bioretention area. Several pretreatment measures are feasible, depending on the scale of the bioretention practice and whether it receives sheet flow, shallow concentrated flow or concentrated flows. The following are appropriate pretreatment options: Micro Bioretention (Rain Gardens) Bioretention Basins 5.5. Conveyance and Overflow Another option is to utilize a low flow diversion or flow splitter at the inlet to allow only the treatment volume peak flow rate to enter the facility. This may be achieved with a weir or curb opening sized for the target flow, in combination with a bypass channel (see Figure 3). Using a weir or curb opening helps minimize clogging and reduces the maintenance frequency. (Further guidance on determining the water quality design peak flow rate will be provided.) 5.6. Filter Media and Surface Cover, The filter media and surface cover are the two most important elements of a bioretention facility in terms of long term performance. There are several key factors to consider in determining an acceptable soil media mixture.
A primary factor in interpreting the desired P-Index of a soil is the bulk density. Saxton et. al. (1986) estimated generalized bulk densities and soil-water characteristics from soil texture. The expected bulk density of the loamy sand soil composition described above should be in the range of 1.6 to 1.7 g/cm3. Therefore, the recommended range for bioretention soil P-index of between 10 and 30 corresponds to a phosphorus content range (mg of P to kg of soil) within the soil media of 7 mg/kg to 23 mg/kg Soils with CECs exceeding 10 are preferred for pollutant removal. Increasing the organic matter content of any soil will help to increase the CEC since it also holds cations like the clays.
Figure 8. Typical Detail - Off-Line Bioretention
5.7. Underdrain & Underground Storage Layer Some Level 2 designs will not use an underdrain (where soil infiltration rates meet minimum standards; see Section 5.2 and Section 2 design tables). For Level 2 designs with an underdrain, an underground storage layer of at 12” should be incorporated below the invert of the underdrain. The depth of the storage layer will depend on the target treatment and storage volumes needed to meet water quality, channel protection, and/or flood protection criteria. However, the bottom of the storage layer must be at least 2 feet above the seasonally high water table. The storage layer should consist of clean, washed #57 stone or an approved infiltration module. All bioretention basins should include observation wells. The observation wells should be tied into any T’s or Y’s in the underdrain system, and should extend upwards to be flush with surface, with a vented cap. In addition, cleanout pipes should be provided if the contributing drainage area exceeds 1 acre. 5.8. Bioretention Planting Plans Native plant species are preferred over non-native species, but some ornamental species may be used for landscaping effect if they are not aggressive or invasive. Some popular native species that work well in bioretention areas and are commercially available can be found in Table 4. Internet links to more detailed bioretention plant lists developed in piedmont and coastal plain communities of the Chesapeake Bay are provided in Table 5. The planting template refers to the form and combination of native trees, shrubs, and perennial ground covers that maintain the appearance and function of the bioretention area. The five most common bioretention templates are as follows:
The choice of which planting template to use depends on the scale of bioretention, the context of the site in the urban environment, the filter depth, the desired landscape amenities and the future owners capability to maintain the landscape. In general, the vegetative goal is to cover up the filter surface with vegetation in a short amount of time. This means that the herbaceous layer is equally or more important than widely spaced trees and shrubs. In the past, many bioretention areas in Virginia did not include enough herbaceous plants. The following additional guidance on developing an effective bioretention landscaping plan is provided: 5.9. Bioretention Material Specifications Table 6 outlines the standard material specifications to construct bioretention areas.
SECTION 6.0 REGIONAL AND SPECIAL CASE DESIGN ADAPTATIONS 6.1 Karst Terrain Active karst regions are found in much of the Ridge and Valley province of the Bay watershed, and complicate both development and stormwater design. While bioretention areas produce less deep ponding than conventional stormwater practices (e.g., ponds and wetlands), Level 2 bioretention designs (i.e., infiltration) are not recommended in any area with a moderate or high risk of sinkhole formation (Hyland, 2005). On the other hand, Level 1 designs that meet separation distance requirements (three feet) and possess an impermeable bottom liner and an underdrain should work well. In general, micro-bioretention and bioretention basins with contributing drainage areas not exceeding 20,000 square feet are preferred (compared to bioretention with larger drainage areas) in order to prevent possible sinkhole formation, although it may be advisable to increase standard setbacks to buildings. 6.2 Coastal Plain The flat terrain, low head and high water table of many coastal plain sites can constrain the application of deeper bioretention areas (particularly Level 2 designs). In these situations, the following design adaptations may be helpful. While these design criteria permit bioretention to be used on a wider range of coastal plain sites, it is important not to force it into marginal sites. Other stormwater practices, such as wet swales, ditch wetland restoration and smaller linear wetlands, are often preferred alternatives for coastal plain sites. 6.3 Steep Terrain Contributing slopes to a bioretention area can be increased to 15% in areas of steep terrain, as long as a two cell design is used to dissipate erosive energy prior to filtering. Designers may also want to terrace a series of bioretention cells to manage runoff across or down a slope. The drop in slope between cells should be limited to a foot, be armored with river stone or suitable equivalent. 6.4 Winter Performance 6.5 Linear Highway Sites Bioretention is a preferred practice for constrained highway right of ways when it is designed as a series of individual on-line or off-line cells. In these situations, the final design closely resembles that of dry swales. Salt tolerant species should be selected if the contributing roadway will be salted in the winter.
SECTION 7: BIORETENTION CONSTRUCTION SEQUENCE AND INSPECTION 7.1. Construction Sequence Construction Stage ESC Controls. Micro-bioretention and small scale bioretention areas should be fully protected by silt fence or construction fencing, particularly if they will rely on infiltration (i.e., have no underdrains). Ideally, bioretention should remain outside the limit of disturbance during construction to prevent soil compaction by heavy equipment. Bioretention basin locations may be used as small sediment traps or basins during construction. However, these must be accompanied by notes and graphic details on the ESC plan identifying the maximum excavation depth at the construction stage being at least 1 foot above the post-construction installation, must contain an underdrain, and show the proper procedures for conversion from a temporary practice to a permanent one, including de-watering, cleanouts and stabilization. 7.2 Bioretention Installation The following is a typical construction sequence to properly install a bioretention basin practice (also see Figure 9). The construction sequence for micro-bioretention is more simplified. These steps may be modified to reflect different bioretention applications or expected site conditions: Step 1. Bioretention may only begin after entire contributing drainage area has been stabilized with vegetation. It may be necessary to block certain curb or other inlets while the bioretention area is being constructed. The proposed site should be checked for existing utilities prior to any excavation. Step 2. The designer and the installer should conduct a preconstruction meeting, and check the boundaries of the contributing drainage area and the actual inlet elevations to ensure they conform to original design. Since other contractors may be responsible for constructing portions of the site, it is quite common to find subtle differences in site grading, drainage and paving elevations that can produce hydraulically important differences for the proposed bioretention area. The designer should clearly communicate any project changes needed during the preconstruction meeting. Step 3. Temporary ESC controls are needed during bioretention installation to divert stormwater away from the bioretention area until it is completed. Special protection measures such as erosion control fabrics may be needed to protect vulnerable side slopes from erosion during the construction process. Step 4. Any pretreatment cells should be excavated first and then sealed to trap sediments Step 5. Excavators or backhoes should work from the sides to excavate the bioretention area to its appropriate design depth and dimensions. Excavating equipment should have arms with adequate reach so they do not have to work inside the footprint of the bioretention area. Contractors should utilize a cell construction approach in larger bioretention basins, whereby the basin is split into 500 to 1,000 sq. ft. temporary cells with a 10-15 foot earth bridge in between, so that cells can be excavated from the side. Step 7. Place the geotextile fabric on the sides of the bioretention area with 6-inch overlap on the sides. If a stone storage layer will be used, place the appropriate depth of #57 stone on the bottom, install the perforated underdrain pipe, pack #57 stone to 3 inches above the underdrain pipe, and add approximately 3 inches of choker stone/pea gravel as a filter between the underdrain and the soil layer. If no stone storage layer is used, start with 6 inches of #57 stone on the bottom, and proceed with the layering as described above. Step 8. Deliver soil media from an approved vendor and store it on an adjacent impervious area or plastic sheeting. Apply the media in 12-inch lifts until desired top elevation of the bioretention area is achieved. Wait a few days to check for settlement, and add additional media as needed. Step 9. Prepare planting holes for any trees and shrubs, install vegetation, and water accordingly. Install any temporary irrigation. Step 10. Place the surface cover in both cells (mulch, river stone or turf), depending on design. If coir or jute matting will be used in lieu of mulch, the matting will need to be installed prior to planting (Step 9) and holes or slits cut in the matting to install the plants. Step 11. Install plant materials as shown in the landscaping plan, and water them during weeks of no rain for the first two months. Step 12. Conduct the final construction inspection (see Section 9.2), and login the GPS coordinates for each facility in local maintenance tracking database.
Figure 9. Typical Biofilter Construction Sequence 7.3 Construction Inspection Inspections during construction are needed to ensure that the bioretention practice is built in accordance with these specifications. Detailed inspection checklists, which include sign-offs by qualified individuals at critical stages of construction, should be used to ensure that the contractor’s interpretation of the plan is consistent with the designer’s intent. An example construction phase inspection checklist for bioretention areas can be accessed at the Center for Watershed Protection website at: www.cwp.org/postconstruction. Go to Tool #6. Some common pitfalls can be avoided by careful construction supervision that focuses on the following key aspects of bioretention installation. The real test for bioretention is after its first big storm. The post-storm inspection should focus on whether the desired sheetflow, shallow concentrated flow or concentrated flow conditions assumed in the plan are realized in the field. Also, inspectors should check that the bioretention areas drains within minimum 6 hour draw down. Minor adjustments are normally needed as a result of this post-storm inspection, such as spot reseeding, gully repair and added armoring at inlets, outfalls and pretreatment devices. SECTION 8: BIORETENTION MAINTENANCE 8.1. Maintenance Agreements Section 4VAC 50-60-124 of the regulations specifies a maintenance agreement to be executed between the owner and the local program. The section requires a schedule of inspections, compliance procedures if maintenance is neglected, notification of the local program upon transfer of ownership, and right-of-entry for local program personnel. For bioretention, the maintenance agreements must contain recommended maintenance tasks and a copy of an annual inspection checklist. When micro-scale bioretention practices are applied on private residential lots, homeowners will need to be educated regarding their routine maintenance needs. A deed restriction or other mechanism enforceable by the qualifying local program must be in place to help ensure that rain gardens and bioretention filters are maintained and not converted or disturbed, as well as pass the knowledge along to any subsequent owners. The mechanism should, if possible, grant authority for local agencies to access the property for inspection or corrective action. 8.2. First Year Maintenance Operations Successful establishment of bioretention areas requires certain tasks be undertaken in the first year. 8.3. Maintenance Inspections It is highly recommended that a spring maintenance inspection and cleanup be conducted at each bioretention area. Table 7 presents some of the key maintenance problems to look for; a more detailed annual maintenance inspection checklist for bioretention areas can be accessed at the Center for Watershed Protection website at: www.cwp.org/postconstruction. Go to Tool #6. 8.4. Routine and Non-Routine Maintenance Tasks Maintenance of bioretention areas should be integrated into routine landscaping maintenance tasks. If landscaping contractors will be expected to perform maintenance, their contracts should contain specifics on unique bioretention landscaping needs, such as maintaining elevation differences needed for ponding, proper mulching, sediment and trash removal, and limited use of fertilizers and pesticides. A customized maintenance schedule must be prepared for each bioretention facility, since the maintenance tasks will differ depending on the scale of bioretention, the landscaping template chosen, and the nature of surface cover. A generalized summary of common maintenance tasks and their frequency is provided in Table 8. The most common non-routine maintenance problem involves standing water.If water remains on the surface for more than 48 hours after a storm, adjustments to the grading may be needed or underdrain repairs may be needed. The surface of the filter bed should also be checked for accumulated sediment or a fine crust that builds up after the first several storm events. There are several methods that can be used to rehabilitate the filter (try the easiest things first, as listed below):
SECTION 9: DESIGN REFERENCES The following references and resources were used to develop this master specification. Lake County, OH Bioretention Guidance Manual CWP. 2007. National Pollutant Removal Performance Database Version 3.0. Center for Watershed Protection, Ellicott City, MD. Schueler, T. 2008. Technical Support for the Baywide Runoff Reduction Method. Chesapeake Stormwater Network. Baltimore, MD www.chesapeakestormwater.net Prince George’s Co., MD Bioretention Manual Maryland Stormwater Design Manual Wisconsin Stormwater Management Technical Standards http://www.dnr.state.wi.us/org/water/wm/nps/stormwater/techstds.htm#Post Hirschman, D., L. Woodworth and S. Drescher. 2009. Technical Report: Stormwater BMPs in Virginia’s James River Basin: An Assessment of Field Conditions & Programs. Center for Watershed Protection. Ellicott City, MD. Hunt, W.F. III and W.G. Lord. 2006. Bioretention Performance, Design, Construction, and Maintenance. North Carolina Cooperative Extension Service Bulletin. Urban Waterways Series. AG-588-5. North Carolina State University. Raleigh, NC. Hyland, S. 2005. Analysis of sinkhole susceptibility and karst distribution in the Northern Shenandoah Valley (Virginia); impacts for LID site suitability models. M.S. Thesis. Virginia Polytechnic Institute and State University. Blacksburg, VA. Minnesota Stormwater Steering Committee (MSSC). 2005. The Minnesota Stormwater Manual. Schueler et al 2007. Urban Stormwater Retrofit Practices. Manual 3 in the Urban Subwatershed Restoration Manual Series. Center for Watershed Protection. Ellicott City, MD. North Shore City 2007. Bioretention Design Guidelines. Sinclair, Knight and Merz. Auckland, New Zealand In addition, the following individuals provided review and input for this version of the specification. Rick Scafidi (EQR), Bill Hunt (NCSU), Scott Thomas (JCC), Dave Hirschman (CWP) Don Rissmeyer (Randy Greer (DENRC), Doug Biesch (WEG) Stuart Stein (GKY), Tim Schueler (MC), Christie Minami (MD SHA). Special thanks to the staff at WEG for providing the design schematics and details. APPENDIX A
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Table A-1: Summary of Stormwater Functions Provided by Urban Bioretention Areas |
||
Stormwater Function |
Level 1 Design |
Level 2 Design |
Annual Runoff Reduction |
40% (for Water Quality credit in the RRM Spreadsheet only) 0% credit for Channel Protection |
NA |
Total Phosphorus Removal 1 |
25% |
NA |
Total Nitrogen Removal 1 |
40% |
NA |
Channel Protection |
None; or if sized according to Bioretention Basin, follow the Bioretention basin, Level 1 criteria. |
|
Flood Mitigation |
None |
|
1 Change in event mean concentration (EMC) through the practice. Actual nutrient mass load removed is the product of the removal rate and the runoff reduction rate. |
||
Figure A1 Stormwater Planters
_files/image032.jpg)
Figure A2 Expanded Tree Pits
_files/image034.jpg)
Figure A3 Stormwater Curb Extensions
_files/image036.jpg)
SECTION A-2: DESIGN TABLES
Table A-2: Urban Bioretention Design Criteria |
Level 1 Design (RR 40 TP: 25 ) |
Sizing (Sec. A-5): |
Underdrain (Sec. A.7) = Schedule 40 PVC with clean-outs |
Maximum Drainage Area = 2,500 ft2 |
Filter media depth minimum = 30 inches; recommended maximum = 48 inches |
Media & Surface Cover (Refer to Sec. A-7) |
Sub-soil testing (Refer to Sec. A-7) |
Inflow = sheetflow, curb cuts, trench drains, roof drains, concentrated flow, or equivalent |
Building setbacks (Sec. A-4) |
Deeded maintenance O&M plan (Sec. 7) |
SECTION A-3: TYPICAL DETAILS
Figure A4: Typical Detail – Urban Bioretention Cross-Section
Ponding depth above 6 inches will require a specific planting plan to ensure appropriate plants (Bioretention Section 5.8)._files/image039.jpg)
_files/image040.jpg)
Figure A5: Expanded Tree Pit Diagram
Portland, Oregon has thorough construction details for stormwater curb extensions and expanded tree pits. These include details for addressing utility house connections.
http://www.portlandonline.com/bes/index.cfm?c=44213&
SECTION A-4: PHYSICAL FEASIBILITY & DESIGN APPLICATIONS
In general, urban bioretention has the same constraints as regular bioretention, along with a few additional constraints as noted below:
Because urban bioretention is installed in a highly urban setting, individual units may be subject to higher public visibility, greater trash loads, pedestrian use, vandalism and even vehicular loads. Therefore, a preventative approach is recommended in their design to address these issues. In addition, designers should clearly recognize the need to perform frequent landscaping maintenance to remove trash, check for clogging, and maintain vegetation. The urban landscaping context may feature naturalized landscaping or a more formal deign. When urbanbioretention is used in sidewalk areas of high foot traffic, designers should not impede pedestrian movement or create a safety hazard. Designers may also install low fences, grates or other measures to prevent damage from pedestrian short-cutting across the practices.
SECTION A5. DESIGN CRITERIA
Urban bioretention practices are similar in function to regular bioretention practices except they are adapted to fit into “containers” within urban landscapes. Therefore, special sizing accommodations are made to allow these practices to fit in very constrained areas where other surface practices may not be feasible.
5.1. Sizing of Urban Bioretention
The required surface area of the Level 1 urban bioretention filter is one half of the treatment volume (Tv); Equation (1) below. This criterion represents a balance between the need to size these structures so as to provide a reasonable alternative in ultra urban settings and the relationship between the surface area size, media permeability, and drawdown requirements. Ideally, urban bioretention facilities are in close proximity to the public or users of the adjacent buildings and/or commercial areas, and thus subjected to increased scrutiny. This provides a theoretical basis for adjusting the clogging factor for the media permeability coefficient (k, ft/day), or an increase in the allowable maximum drawdown time, resulting in the smaller sizing. However, as a result, Level 1 urban bioretention will only count towards water quality credit through the 40% volume reduction and/or the 25% TP pollutant removal. There is no credit given to channel protection due to the reduced surface area and storage volume.
Level 1 Urban Bioretention:
(1) SA (ft2) = Tv (ft3) / 2.0 ft
Where
Tv = is required treatment volume in cubic feet
SA= surface area of bioretention area in square feet
5.2 General Design Criteria for Urban Bioretention
Design of urban bioretention should follow the general guidance presented in the main part of this design specification. The actual geometric design of urban bioretention is usually dictated by other landscape elements such as buildings, sidewalk widths, utility corridors, retaining walls, etc. Designers can divert fractions of the runoff volume from small impervious surfaces into micro-bioretention units that are integrated with the overall landscape design. Inlets and outlets should be located as far apart as possible. Some additional design guidance that applies to all variations of urban bioretention is presented below:
5.3 Specific Design Issues for Stormwater Planters
Since stormwater planters are often located near building foundations, waterproofing by a watertight concrete shell or an impermeable liner is required to prevent seepage.
5.4 Specific Design Issues for Expanded Tree Pits
5.5 Specific Design Issues for Stormwater Curb Extensions
Roadway stability can be a design issue with stormwater curb extensions.Design standards or roadway drainage should be consulted. It may be necessary to provide a barrier to keep water from saturating the road’s sub-base, and demonstrate it is capable of supporting H-20 loads.
5.6 Planting and Landscaping Considerations
The degree of landscaping maintenance that can be provided will determine some of the planting choices for urban bioretention areas. The planting cells can be formal gardens or naturalized landscapes.
In areas where less maintenance will be provided and where trash accumulation in shrubbery or herbaceous plants is a concern, consider a “turf and trees” landscaping model. Spaces for herbaceous flowering plants can be included. This may be attractive at a community entrance location.
Native trees or shrubs are preferred for urban bioretention areas, although some ornamental species may be used. As with regular bioretention, the selected perennials, shrubs, and trees must be tolerant of salt, drought, and inundation. Additionally, tree species should be those that are known to survive well in the compacted soils and polluted air and water of an urban landscape.
SECTION A-6 URBAN BIORETENTION MATERIAL SPECIFICATIONS
Please consult the main part of this design specification for the typical materials needed for filter media, stone, mulch and other bioretention features. The unique components for urban bioretention may include the inlet control device, a concrete box or other containing shell, protective grates and an underdrain that daylights to another stormwater practice or connects to the storm drain system. The underdrain should:
The construction sequence and inspection requirements for urban bioretention are generally the same as micro-bioretention practices. Please consult the construction sequence and inspection checklists outlined in the main part of this specification. In cases where urban bioretention is constructed in the road or right of way, the construction sequence may need to be adjusted to account for traffic control, pedestrian access and utility notification.
Urban bioretention areas should only be constructed after the drainage area to the facility is completely stabilized. The specified growth media should be placed by hand with minimal compaction in order to maintain the porosity of the media. Spreading should be by hand. The media should be placed in 8 to 12 inch lifts with no machinery allowed over the media during or after construction. The media should be overfilled above the proposed surface elevation as needed to allow for natural settlement. Lifts may be lightly watered to encourage settlement. After the final lift is placed, the media should be raked to level it, saturated, and allowed to settle for at least one week prior to installation of plant materials.
SECTION A-8 URBAN BIORETENTION MAINTENANCE
Routine operation and maintenance are essential to gain public acceptance of highly visible urban bioretention areas. Weeding, pruning, and trash removal should be done as needed to maintain the aesthetics for community acceptance. During drought conditions, it may be necessary to water the plants as would be the case with any landscaped area.
To ensure proper performance, inspectors should check that stormwater infiltrates properly into the soil within 24 hours after a storm. If excessive water ponding is observed, corrective measures include inspection for soil compaction and underdrain clogging. Please consult the maintenance inspection checklists and ongoing maintenance tasks as outlined in the main part of this design specification
A-9 DESIGN REFERENCES
The following references and resources were used to develop this additional specification:
Center for Watershed Protection. 2006. Urban Watershed Forestry Manual Part 2: Conserving and Planting Trees at Development Sites. Ellicott City, MD
http://www.cwp.org/forestry/index.htm
City of Portland, Bureau of Environmental Services. (Portland BES). 2004. Portland Stormwater Management Manual. Portland, OR. http://www.portlandonline.com/bes/index.cfm?c=dfbcc
Credit Valley Conservation. 2008. Credit River Stormwater Management Manual. Mississauga, Ontario
Northern Virginia Regional Commission. 2007. Low Impact Development Supplement to the Northern Virginia BMP Handbook. Fairfax, Virginia
Saxton, K.E., W.J. Rawls, J.S. Romberger, and R.I. Papendick. 1986. Estimating generalized soil-water characteristics from texture. Soil Sci. Soc. Am. J. 50(4):1031-1036
Schueler, T., D. Hirschman, M. Novotney and J. Zielinski. 2007. Urban stormwater retrofit practices. Manual 3 in the Urban Subwatershed Restoration Manual Series. Center for Watershed Protection, Ellicott City, MD
APPENDIX B
A-10. ADDITIONAL DETAILS AND SCHEMATICS FOR REGULAR BIORETENTION
_files/image045.jpg)
_files/image047.jpg)