SECTION 1: DESCRIPTION
Individual bioretention areas can serve highly impervious drainage areas less than two (2) acres in size. Surface runoff is directed into a shallow landscaped depression that incorporates many of the pollutant removal mechanisms that operate in forested ecosystems. The primary component of a bioretention practice is the filter bed, which has a mixture of sand, soil, and organic material as the filtering media with a surface mulch layer. During storms, runoff temporarily ponds 6 to 12 inches above the mulch layer and then rapidly filters through the bed. Normally, the filtered runoff is collected in an underdrain and returned to the storm drain system. The underdrain consists of a perforated pipe in a gravel layer installed along the bottom of the filter bed. A bioretention facility with an underdrain system is commonly referred to as a Bioretention Filter.
Bioretention can also be designed to infiltrate runoff into native soils. This can be done at sites with permeable soils, a low groundwater table, and a low risk of groundwater contamination. This design features the use of a "partial exfiltration" system that promotes greater groundwater recharge. Underdrains are only installed beneath a portion of the filter bed, above a stone "sump" layer, or eliminated altogether, thereby increasing stormwater infiltration. A bioretention facility without an underdrain system, or with a storage sump in the bottom is commonly referred to as a Bioretention Basin.
Small-scale or Micro-Bioretention used on an individual residential lot is commonly referred to as a Rain Garden.
SECTION 2: PERFORMANCE
Bioretention creates a good environment for runoff reduction, filtration, biological uptake, and microbial activity, and provides high pollutant removal. Bioretention can become an attractive landscaping feature with high amenity value and community acceptance. The overall stormwater functions of the bioretention are summarized in Table 9.1.
Table 9.1. Summary
of Stormwater Functions Provided by Bioretention Basins
|
Stormwater Function |
Level 1 Design |
Level 2 Design |
| Annual Runoff Reduction (RR) | 40% |
80% |
| Total Phosphorus (TP) Removal 1 | 25% |
50% |
| Total Nitrogen (TN) Removal 1 | 40% |
60% |
| Channel and Flood Protection |
| |
| 1
Change in event mean concentration (EMC) through the practice. Actual
nutrient mass load removed is the product of the removal rate and the
runoff reduction rate(see Table 1 in the Introduction to the New
Virginia Stormwater Design Specifications).
2 NRCS TR-55 Runoff Equations 2-1 thru 2-5 and Figure 2-1 can be used to compute a curve number adjustment for larger storm events based on the retention storage provided by the practice(s). | ||
The most important design factor to consider when applying bioretention to development sites is the scale at which it will be applied, as follows:
Micro-Bioretnetion or Rain Gardens. These are small, distributed practices designed to treat runoff from small areas, such as individual rooftops, driveways and other on-lot features in single-family detatched residential developments. Inflow is typically sheet flow, or can be concentrated flow with energy dissipation, when located at downspouts.
Bioretention Basins. These are structures treating parking lots and/or commercial rooftops, usually in commercial or institutional areas. Inflow can be either sheetflow or concentrated flow. Bioretention basins may also be distributed throughout a residential subdivision, but ideally they should be located in common area or within drainage easements, to treat a combination of roadway and lot runoff.
Urban Bioretention. These are structures such as expanded tree pits, curb extensions, and foundation planters located in ultra-urban developed areas such as city streetscapes. Please refer to Appendix 9-A of this specification for design criteria for Urban Bioretention.

The major design goal for bioretention is to maximize runoff volume reduction and nutrient removal. To this end, designers may choose to go with the baseline design (Level 1) or choose an enhanced design (Level 2) that maximizes nutrient and runoff reduction. If soil conditions require an underdrain, bioretention areas can still qualify for the Level 2 design if they contain a stone storage layer beneath the invert of the underdrain.
Both stormwater quality and quantity credits are accounted for in the Runoff Reduction Method (RRM) spreadsheet. The water quality credit represents an annual load reduction as a combination of the annual reduction of runoff volume (40% and 80% from Level 1 and Level 2 designs, respectively) and the reduction in the pollutant event mean concentration (EMC) (25% and 50% from Level 1 & 2 designs, respectively).
To compute the water quantity reduction for larger storm events, the designer can similarly use the RRM spreadsheet or, as an option, the designer may choose to compute the adjusted curve number associated with the retention storage using the TR-55 Runoff Equations, as noted in Table 9.1. The adjusted curve number is then used to compute the peak discharge for the required design storms.
Tables 9.2 and 9.3 outline the Level 1 and 2 design guidelines for the two scales of bioretention design.
Table 9.2. Micro-Bioretention
(Rain Garden) Design Criteria1
|
Level 1 Design (RR 40 TP:
25) |
Level 2 Design
(RR: 80 TP: 50) |
| Sizing: Filter surface area (sq. ft.) = 3% 2 of the contributing drainage area (CDA). | Sizing: Filter surface area (sq. ft.) = 4% 2 of the CDA (can be divided into different cells at downspouts). |
Maximum
contributing drainage area = 0.5 acres; 25% Impervious Cover (IC) 2 | |
One cell
design (can be divided into smaller cells at downspout locations) 2 | |
Maximum
Ponding Depth = 6 inches | |
| Filter Media Depth minimum = 18 inches; Recommended maximum = 36 inches | Filter Media Depth minimum = 24 inches; Recommended maximum = 36 inches |
| Media: mixed on-site or supplied by vendor | Media: supplied by vendor |
All Designs:
Media mix tested for an acceptable phosphorus index (P-Index) of between 10 and 30, OR Between 7 and 21 mg/kg of P in the soil media | |
| Sub-soil testing: not needed if an underdrain is used; Min infiltration rate > 1 inch/hour in order to remove the underdrain requirement. | Sub-soil testing: one per practice; Min infiltration rate > 1/2 inch/hour; Min infiltration rate > 1 inch/hour in order to remove the underdrain requirement. |
| Underdrain: corrugated HDPE or equivalent. | Underdrain: corrugated HDPE or equivalent, with a minimum 6-inch stone sump below the invert; OR none, if soil infiltration requirements are met |
Clean-outs:
not needed | |
Inflow:
sheetflow or roof leader | |
| Pretreatment: external (leaf screens, grass filter strip, energy dissipater, etc.). | Pretreatment: external plus a grass filter strip |
| Vegetation: turf, herbaceous, or shrubs (min = 1 out of those 3 choices). | Vegetation: turf, herbaceous, shrubs, or trees (min = 2 out of those 4 choices). |
Building
setbacks: 10 feet down-gradient; 25 feet up-gradient | |
| 1 Consult Appendix
9-A for design criteria for Urban
Bioretention Practices. 2 Micro-Bioretention (Rain Gardens) can be located at individual downspout locations to treat up to 1,000 sq. ft. of impervious cover (100% IC); the surface area is sized as 5% of the roof area (Level 1) or 6% of the roof area (Level 2), with the remaining Level 1 and Level 2 design criteria as provided in Table 9.2. If the Rain Garden is located so as to capture multiple rooftops, driveways, and adjacent pervious areas, the sizing rules within Table 9.2 should apply. | |
|
Level 1 Design (RR 40 TP: 25 ) |
Level 2 Design
(RR: 80 TP: 50) | |
|
Sizing (Section
6.1):
Surface Area (sq. ft.) = (Tv - the volume reduced by an upstream BMP) / Storage Depth 1 |
Sizing (Section 6.1):
Surface Area (sq. ft.) = [(1.25)(Tv) - the volume reduced by an upstream BMP] /Storage Depth 1 | |
Recommended
maximum contributing drainage area = 2.5 acres | ||
| Maximum Ponding Depth = 6 to 12 inches 2 | Maximum Ponding Depth = 6 to 12 inches 2 | |
| Filter Media Depth minimum = 24 inches; recommended maximum = 6 feet | Filter Media Depth minimum = 36 inches; recommended maximum = 6 feet | |
Media
& Surface Cover (Section 6.6) = supplied
by vendor; tested for acceptable phosphorus index (P-Index) of between 10 and 30, OR Between 7 and 21 mg/kg of P in the soil media | ||
| Sub-soil Testing (Section 6.2): not needed if an underdrain used; Min infiltration rate > 1/2 inch/hour in order to remove the underdrain requirement. | Sub-soil Testing (Section 6.2): one per 1,000 sq. ft. of filter surface; Min infiltration rate > 1/2 inch/hour in order to remove the underdrain requirement. | |
| Underdrain (Section 6.7) = Schedule 40 PVC with clean-outs | Underdrain & Underground Storage Layer (Section 6.7) = Schedule 40 PVC with clean outs, and a minimum 12-inch stone sump below the invert; OR, none, if soil infiltration requirements are met (Section 6.2) | |
Inflow:
sheetflow, curb cuts, trench drains, concentrated flow, or the equivalent | ||
| Geometry
(Section 6.3): Length of shortest flow path/Overall length = 0.3; OR, other design methods used to prevent short-circuiting; a one-cell design (not including the pre-treatment cell). |
Geometry (Section 6.3): Length of shortest flow path/Overall length = 0.8; OR, other design methods used to prevent short-circuiting; a two-cell design (not including the pretreatment cell). | |
| Pre-treatment (Section 6.4): a pretreatment cell, grass filter strip, gravel diaphragm, gravel flow spreader, or another approved (manufactured) pre-treatment structure. | Pre-treatment (Section 6.4): a pretreatment cell plus one of the following: a grass filter strip, gravel diaphragm, gravel flow spreader, or another approved (manufactured) pre-treatment structure. | |
| Conveyance & Overflow (Section 6.5) | Conveyance & Overflow (Section 6.5) | |
| Planting Plan (Section 6.8): a planting template to include turf, herbaceous vegetation, shrubs, and/or trees to achieve surface area coverage of at least 75% within 2 years. | Planting Plan (Section 6.8): a planting template to include turf, herbaceous vegetation, shrubs, and/or trees to achieve surface area coverage of at least 90% within 2 years. If using turf, must combine with other types of vegetation 1. | |
Building
Setbacks 3 (Section 5):
0 to 0.5 acre CDA = 10 feet if down-gradient from building or level (coastal plain); 50 feet if up-gradient. 0.5 to 2.5 acre CDA = 25 feet if down-gradient from building or level (coastal plain); 100 feet if up-gradient. (Refer to additional setback criteria in Section 5) | ||
Deeded
Maintenance O&M Plan (Section 8) | ||
1 Storage depth is the sum of the Void Ratio (Vr) of the soil media and gravel layers multiplied by their respective depths, plus the surface ponding depth. Refer to Section 6.1. 2 A ponding depth of 6 inches is preferred. Ponding depths greater than 6 inches will require a specific planting plan to ensure appropriate plant selection (Section 6.8). 3 These are recommendations for simple building foundations. If an in-ground basement or other special conditions exist, the design should be reviewed by a licensed engineer. Also, a special footing or drainage design may be used to justify a reduction of the setbacks noted above. | ||
SECTION 3: TYPICAL DETAILS
Figures 9.2 through 9.5 provide some typical details for several bioretention configurations. Also see additional details in Appendix 9-B of this design specification.

Figure 9.2. Residential
Rooftop Treatment - Plan View:
(a) Simple Disconnection
to downstream Raingarden;
(b) Disconnection
- Alternative Practice: Raingarden;
(c) Disconnection
- Alternative Practice: Compost
Amended Flow Path
to downstream Raingarden

Figure 9.3A. Residential
Rooftop Disconnection - Section View:
(a)
Simple Disconnection to downstream Raingarden; (b)
Disconnection -
Alternative
Practice: Compost Amended Flow Path to downstream Raingarden

Figure 9.3B. Typical Micro-Bioretention Basin (Rain Garden) Level I and Level II - Section View:

Figure 9.4a: Typical Detail of Bioretention Basin Level 1 Design

Figure 9.4b: Typical Detail of Bioretention Basin Level 2 Design

Figure
9.6. Typical Detail of a Bioretention Basin within the
Upper Shelf of an ED Pond

Figure 9.7 - Pretreatment I and II - Grass Filter for Sheet Flow

Figure 9.8 - Pretreatment - Gravel Diaphragm for Sheet Flow from Impervious or Pervious

Figure 9.9: Pre-Treatment - Gravel Flow Spreader for Concentrated Flow
SECTION 5: PHYSICAL FEASIBILITY & DESIGN APPLICATIONS
5.1 Physical Feasibility
Bioretention can be applied in most soils or topography, since runoff simply percolates through an engineered soil bed and is returned to the stormwater system. Key constraints with bioretention include the following:
Available Space. Planners and designers can assess the feasibility of using bioretention facilities based on a simple relationship between the contributing drainage area and the corresponding required surface area. The bioretention surface area will be approximately 3% to 6% of the contributing drainage area, depending on the imperviousness of the CDA and the desired bioretention design level.
Site Topography. Bioretention is best applied when the grade of contributing slopes is greater than 1% and less than 5%.
Available Hydraulic Head. Bioretention is fundamentally constrained by the invert elevation of the existing conveyance system to which the practice discharges (i.e., the bottom elevation needed to tie the underdrain from the bioretention area into the storm drain system. In general, 4 to 5 feet of elevation above this invert is needed to create the hydraulic head needed to drive stormwater through a proposed bioretention filter bed. Less hydraulic head is needed if the underlying soils are permeable enough to dispense with the underdrain.
Water Table. Bioretention should always be separated from the water table to ensure that groundwater does not intersect the filter bed. Mixing can lead to possible groundwater contamination or failure of the bioretention facility. A separation distance of 2 feet is recommended between the bottom of the excavated bioretention area and the seasonally high ground water table. The separation distance may be reduced to 12 inches in coastal plain residential settings (Refer to Section 7.2 - Regional Adaptations).
Utilities. Designers should ensure that future tree canopy growth in the bioretention area will not interfere with existing overhead utility lines. Interference with underground utilities should also be avoided, particularly water and sewer lines. Local utility design guidance should be consulted in order to determine the horizontal and vertical clearance required between stormwater infrastructure and other dry and wet utility lines.
Soils. Soil conditions do not constrain the use of bioretention, although they determine whether an underdrain is needed. Impermeable soils in Hydrologic Soil Group (HSG) B, C or D usually require an underdrain, whereas HSG A soils generally do not. When designing a bioretention practice, designers should verify soil permeability by using the on-site soil investigation methods provided in Appendix 8-A of Stormwater Design Specification No. 8 (Infiltration).
Contributing Drainage Area. Bioretention cells work best with smaller contributing drainage areas, where it is easier to achieve flow distribution over the filter bed. Typical drainage area size can range from 0.1 to 2.5 acres and consist of up to 100% impervious cover. Three scales of bioretention are defined in this specification: (1) micro-bioretention or Rain Gardens (up to 0.5 acre contributing drainage area); (2) bioretention basins (up to 2.5 acres of contributing drainage area); and (3) Urban Bioretention (Appendix 9-A). Each of these has different design requirements (refer to Tables 9.2 and 9.3 above). The maximum drainage area to a single bioretention basin or single cell of a bioretention basin is 5 acres, with a maximum recommended impervious cover of 2.5 acres (50% impervious cover) due to limitations on the ability of bioretention to effectively manage large volumes and peak rates of runoff. However, if hydraulic considerations are adequately addressed to manage the potentially large peak inflow of larger drainage areas (such as off-line or low-flow diversions, forebays, etc.), there may be case-by-case instances where the plan approving authority may allow these recommended maximums to be adjusted. In such cases, the bioretention facility should be located within the drainage area so as to capture the Treatment Volume (Tv) equally from the entire contributing area, and not fill the entire volume from the immediately adjacent area, thereby bypassing the runoff from the more remote portions of the site.
Hotspot Land Uses. Runoff from hotspot land uses should not be treated with infiltrating bioretention (i.e., constructed without an underdrain). For a list of potential stormwater hotspots, please consult Section 10.1 of Stormwater Design Specification No. 8 (Infiltration). An impermeable bottom liner and an underdrain system must be employed when bioretention is used to receive and treat hotspot runoff.
Floodplains. Bioretention areas should be constructed outside the limits of the ultimate 100-year floodplain.
No Irrigation or Baseflow. The planned bioretention area should not receive baseflow, irrigation water, chlorinated wash-water or other such non-stormwater flows that are not stormwater runoff.
Setbacks. To avoid the risk of seepage, do not allow bioretention areas to be hydraulically connected to structure foundations or pavement. Setbacks to structures and roads vary, based on the scale of the bioretention design (see Table 9.2 above). At a minimum, bioretention basins should be located a horizontal distance of 100 feet from any water supply well (50 feet if the biofilter is lined), 50 feet from septic systems (20 feet if the biofilter is lined), and at least 5 feet from down-gradient wet utility lines. Dry utility lines such as gas, electric, cable and telephone may cross under bioretention areas if they are double-cased.
5.2 Potential Bioretention Applications
Bioretention can be used wherever water can be conveyed to a surface area. Bioretention has been used at commercial, institutional, and residential sites in spaces that are traditionally pervious and landscaped. It should be noted that special care must be taken to provide adequate pre-treatment for bioretention cells in space-constrained high traffic areas. Typical locations for bioretention include the following:
Parking lot islands. The parking lot grading is designed for sheet flow towards linear landscaping areas and parking islands between rows of spaces. Curb-less pavement edges can be used to convey water into a depressed island landscaping area. Curb cuts can also be used for this purpose, but they are more prone to blockage, clogging and erosion.
Parking lot edge. Small parking lots can be graded so that flows reach a curb-less pavement edge or curb cut before reaching catch basins or storm drain inlets. The turf at the edge of the parking lot functions as a filter strip to provide pre-treatment for the bioretention practice. The depression for bioretention is located in the pervious area adjacent to the parking lot.
Road medians, roundabouts, interchanges and cul-de-sacs. The road cross-section is designed to slope towards the center median or center island rather than the outer edge, using a curb-less edge.
Right-of-way or commercial setback. A linear configuration can be used to convey runoff in sheet flow from the roadway, or a grass channel or pipe may convey flows to the bioretention practice.
Courtyards. Runoff collected in a storm drain system or roof leaders can be directed to courtyards or other pervious areas on site where biorention can be installed.
Individual residential lots. Roof leaders can be directed to small bioretention areas, often called "rain gardens," located at the front, side, or rear of a home in a drainage easement. For smaller lots, the front yard bioretention corridor design may be preferable (See Stormwater Design Specification No. 1: Rooftop Disconnection).
Unused pervious areas on a site. Storm flows can be redirected from a a storm drain pipe to discharge into a bioretention area.
Dry Extended Detention (ED) basin. A bioretention cell can be located on an upper shelf of an extended detention basin, after the sediment forebay, in order to boost treatment. Depending on the ED basin design, the designer may choose to locate the bioretention cell in the bottom of the basin. However, the design must carefully account for the potentially deeper ponding depths (greater than 6 or 12 inches) associated with extended detention.
Retrofitting. Numerous options are available to retrofit bioretention in the urban landscape, as described in Profile Sheet ST-4 of Schueler et al (2007).
SECTION 6: DESIGN CRITERIA
6.1. Sizing of Bioretention Practices
6.1.1 Stormwater Quality
Sizing of the surface area (SA) for bioretention practices is based on the computed Treatment Volume (Tv) of the contributing drainage area and the storage provided in the facility. The required surface area (in square feet) is computed as the Treatment Volume (in cubic feet) divided by the equivalent storage depth (in feet). The equivalent storage depth is computed as the depth of media, gravel, or surface ponding (in feet) multiplied by the accepted void ratio.
The accepted Void Ratios (Vr) are (see Figure 9.10 below):
Bioretention Soil Media Vr = 0.25 |
Gravel Vr = 0.40 |
Surface Storage Vr = 1.0 |
The equivalent storage depth for Level 1 with a 6-inch surface ponding depth and a 12-inch gravel layer is therefore computed as:
Equation 9.1. Bioretention Level 1 Design Storage Depth
![]()
And the equivalent storage depth for Level 2 with a 6-inch surface ponding depth and a 12-inch gravel layer is computed as:
Equation 9.2. Bioretention Level 2 Design Storage Depth
![]()

Figure 9.10. Typical Bioretention Section with Void Ratios for Volume Computations
Therefore, the Level 1 Bioretention Surface Area (SA) is computed as:
Equation 9.3. Bioretention Level 1 Design Surface Area
![]()
And the Level 2 Bioretention Surface Area is computed as:
Equation 9.4. Bioretention Level 2 Design Surface Area
![]()
Where:
(NOTE: Rv = the composite runoff coefficient from the RR Method)
Equations 9.1 through 9.4 should be modified if the storage depths of the soil media, gravel layer, or ponded water vary in the actual design or with the addition of any surface or subsurface storage components (e.g., additional area of surface ponding, subsurface storage chambers, etc.).
6.1.2 Stormwater Quantity
The water quality Treatment Volume (Tv) can be counted as part of the Channel Protection Volume or Overbank Flood Protection Volume to satisfy stormwater quantity control requirements. In addition, designers may be able to create additional surface storage by expanding the surface ponding footprint in order to accommodate a greater quantity credit for channel and/or flood protection, without necessarily increasing the soil media footprint. In other words, the engineered soil media would only underlay part of the surface area of the bioretention (see Figure 9.10 above).
In this regard, the ponding footprint can be increased as follows to allow for additional storage:
These values may be modified as additional data on the long term permeability of bioretention filters becomes available.
6.2. Soil Infiltration Rate Testing
In order to determine if an underdrain will be needed, one must measure the infiltration rate of subsoils at the invert elevation of the bioretention area, as noted in the soil testing requirements for each scale of bioretention, in Design Tables 9.2 and 9.3 above. The infiltration rate of subsoils must exceed 1 inch per hour in order to dispense with the underdrain requirement for Rain Gardens, and 1/2 inch per hour for bioretention basins. On-site soil infiltration rate testing procedures are outlined in Appendix 8-A of the Stormwater Design Specification No. 8 (Infiltration). Soil testing is not needed for Level 1 bioretention areas, where an underdrain is used.
6.3. BMP Geometry
Bioretention
basins must be designed with an internal flow path geometry such that
the treatment mechanisms provided by the bioretention are not bypassed
or short-circuited. Examples of short-circuiting include inlets or curb
cuts that are very close to outlet structures (see Figure 9.11
below), or incoming flow that is diverted immediately to the underdrain
through stone layers. Short-circuiting can be particularly problematic
when there are multiple curb cuts or inlets.
![]() |
![]() |
Figure 9.11.
Examples of Short-Circuiting at Bioretention Facilities
In order for these bioretention areas to have an acceptable internal geometry, the "travel time" from each inlet to the outlet should be maximized, and incoming flow must be distributed as evenly as possible across the filter surface area.
One important characteristic is the length of the shortest flow path compared to the overall length, as shown in Figure 9.12 below. In this figure, the ratio of the shortest flow path to the overall length is represented as:
Equation 9.5. Ratio of Shortest Flow Path to Overall Length
SFP / L
Where:

For Level 1 designs, the SFP/L ratio must be 0.3 or greater; the ratio must be 0.8 or greater for Level 2 designs. In some cases, due to site geometry, some inlets may not be able to meet these ratios. However, the drainage area served by such inlets should constitute no more than 20% of the contributing drainage area. Alternately, the designer may incorporate other design features that prevent short-circuiting, including features that help spread and distribute runoff as evenly as possible across the filter surface.
Note: Local reviewers may waive or modify the guideline for the shortest flow path ratio in cases where (1) the outlet structure within the bioretention area is raised above the filter surface to the ponding depth elevation; and (2) the filter surface is flat.
With regard to the first condition stated in the note above, field experience has shown that soil media immediately around a raised outlet structure is prone to scouring, erosion and, thus, short-circuiting of the treatment mechanism. For example, water can flow straight down through scour holes or sinkholes to the underdrain system (Hirschman et al., 2009). Design options should be used to prevent this type of scouring. One example is shown in Figure 9.13.

Figure 9.13. Typical
Detail of how to prevent bypass
or short-circuiting
around the overflow structure
The designer should ensure that incoming flow is spread as evenly as possible across the filter surface to maximize the treatment potential.
6.4. Pre-treatment
Pre-treatment of runoff entering bioretention areas is necessary to trap coarse sediment particles before they reach and prematurely clog the filter bed. Pre-treatment measures must be designed to evenly spread runoff across the entire width of the bioretention area. Several pre-treatment measures are feasible, depending on the scale of the bioretention practice and whether it receives sheet flow, shallow concentrated flow or deeper concentrated flows. The following are appropriate pretreatment options:
For Micro Bioretention (Rain Gardens):
For Bioretention Basins:
6.5. Conveyance and Overflow
For On-line bioretention: An overflow structure should always be incorporated into on-line designs to safely convey larger storms through the bioretention area. The following criteria apply to overflow structures:
Off-line bioretention: Off-line designs are preferred (see Figure 9.14 for an example). One common approach is to create an alternate flow path at the inflow point into the structure such that when the maximum ponding depth is reached, the incoming flow is diverted past the facility. In this case, the higher flows do not pass over the filter bed and through the facility, and additional flow is able to enter as the ponding water filtrates through the soil media.

Figure 9.14. Typical
Details for Off-Line Biofiltrattion
Another option is to utilize a low-flow diversion or flow splitter at the inlet to allow only the Treatment Volume to enter the facility. This may be achieved with a weir or curb opening sized for the target flow, in combination with a bypass channel. Using a weir or curb opening helps minimize clogging and reduces the maintenance frequency. (Further guidance on determining the Treatment Volume design peak flow rate will be necessary in order to ensure proper design of the diversion structure.)
6.6. Filter Media and Surface Cover
The filter media and surface cover are the two most important elements of a bioretention facility in terms of long-term performance. The following are key factors to consider in determining an acceptable soil media mixture.
A primary factor in interpreting the desired P-Index of a soil is the bulk density. Saxton et. al. (1986) estimated generalized bulk densities and soil-water characteristics from soil texture. The expected bulk density of the loamy sand soil composition described above should be in the range of 1.6 to 1.7 g/cu. cm. Therefore, the recommended range for bioretention soil P-index of between 10 and 30 corresponds to a phosphorus content range (mg of P to kg of soil) within the soil media of 7 mg/kg to 23 mg/kg.
6.7. Underdrain and Underground Storage Layer
Some Level 2 designs will not use an underdrain (where soil infiltration rates meet minimum standards; see Section 6.2 and Section 3 design tables). For Level 2 designs with an underdrain, an underground storage layer of at 12 inches should be incorporated below the invert of the underdrain. The depth of the storage layer will depend on the target treatment and storage volumes needed to meet water quality, channel protection, and/or flood protection criteria. However, the bottom of the storage layer must be at least 2 feet above the seasonally high water table. The storage layer should consist of clean, washed #57 stone or an approved infiltration module.
All bioretention basins should include observation wells. The observation wells should be tied into any T's or Y's in the underdrain system, and should extend upwards to be flush with the surface, with a vented cap. In addition, cleanout pipes should be provided if the contributing drainage area exceeds 1 acre.
6.8. Bioretention Planting Plans
A landscaping plan must be provided for each bioretention area. Minimum plan elements shall include the proposed bioretention template to be used, delineation of planting areas, the planting plan, including the size, the list of planting stock, sources of plant species, and the planting sequence, including post-nursery care and initial maintenance requirements. It is highly recommended that the planting plan be prepared by a qualified landscape architect, in order to tailor the planting plan to the site-specific conditions.
Native plant species are preferred over non-native species, but some ornamental species may be used for landscaping effect if they are not aggressive or invasive. Some popular native species that work well in bioretention areas and are commercially available can be found in Table 9.4. Internet links to more detailed bioretention plant lists developed in piedmont and coastal plain communities of the Chesapeake Bay region are provided in Table 9.5.
The planting template refers to the form and combination of native trees, shrubs, and perennial ground covers that maintain the appearance and function of the bioretention area. The six most common bioretention templates are as follows:
Table 9.4. Popular Native Plant Materials for Bioretention
|
Perennials/Herbaceous |
Shrubs |
Trees |
| Virginia Wild Rye (Elymus virginicus) |
Common Winterberry (Ilex verticillatta) |
River Birch (Betula nigra) |
| Redtop Grass (Agrostis alba) |
Inkberry (Ilex glabra) |
Red Maple (Acer rubrum) |
| Swamp Milkweed (Asclepias incarnata) |
Sweet Pepperbush (Clethra ainifolia) |
Pin Oak (Quercus palustris) |
| Switchgrass (Panicum virgatum) |
Wax Myrtle (Myrica cerifera) |
Willow Oak (Quercus phellos) |
| Cardinal Flower (Lobelia cardinalis) |
Virginia Sweetspire (Itea virginica) |
Sweetgum (Liquidambar styraciflua) |
| Common Three Square (Scirpus americanus) |
Swamp Azeala (Azeala viscosum) |
Black Willow (Salix nigra) |
| Sensitive Fern (Onoclea sensibilis) |
Button Bush (Cephalanthus occidentalis) |
Grey Birch (Betula populifolia) |
| Blue Flag (Iris versicolor) |
Black Haw (Virburnum prunifolium)) |
Black Gum (Nyassa sylvatica) |
| Woolgrass (Scirpus cyperninus) |
Indigo Bush (Amorpha fruticosa) |
Sycamore (Platanus occidentalis) |
| Indian Grass (Sorghastrum nutans) |
Arrowwood (Virburum dentatum) |
Green Ash (Fraxinus pennsylvanica |
| Marsh Marigold (Caltha palustris) |
Sweetbay Magnolia* (Magnolia virginiana) | |
|
Joe Pye Weed (Eupatorium purpureum) |
Atlantic White Cedar* (Charnaecyparis thyoides) | |
| Turk's cap lily (Lilium superbum) |
Bald Cypress* (Taxodium distichum) | |
| Bee Balm (Mornarda didyma) |
Grey Dogwood (Cornus racernosa) | |
| Northern Sea Oats (Chasmanthium latifolium) |
Smooth Alder (Alnus serrulata)) | |
| Serviceberry (Amelanchier canadensis) | ||
| Redbud (Cercis candensis) | ||
| Box Elder (Acer negundo) | ||
| Fringe Tree (Chionanthus virginicus) | ||
| Note:
Prior to selection, please consult bioretention plant lists for more
detailed information regarding inundation, drought and salt tolerance
for each species. * most applicable to the coastal plain | ||
Fairfax County, VA https://166.94.9.135/dpwes/ Prince Georges County,
MD |
The choice of which planting template to use depends on the scale of bioretention, the context of the site in the urban environment, the filter depth, the desired landscape amenities, and the future owner's capability to maintain the landscape. In general, the vegetative goal is to cover up the filter surface with vegetation in a short amount of time. This means that the herbaceous layer is equally or more important than widely-spaced trees and shrubs. In the past, many bioretention areas in Virginia did not include enough herbaceous plants.
The following additional guidance is provided regarding developing an effective bioretention landscaping plan:
6.9. Bioretention Material Specifications
Table 9.6 outlines the standard material specifications used to construct bioretention areas.
Table 9.6. Bioretention
Material Specifications
|
Material |
Specification |
Notes |
Filter Media Composition |
Filter Media to contain:
|
The volume of filter media based on 110% of the plan volume, to account for settling or compaction. |
Filter Media Testing |
P-Index range = 10-30, OR Between 7 and 21 mg/kg of P in the soil media. CECs greater than 10 |
The media must be procured from approved filter media vendors. |
Mulch Layer |
Use aged, shredded hardwood bark mulch | Lay a 2 to 3 inch layer on the surface of the filter bed. |
Alternative Surface Cover |
Use river stone or pea gravel, coir and jute matting, or turf cover. | Lay a 2 to 3 inch layer of to suppress weed growth. |
Top Soil
For Turf Cover |
Loamy sand or sandy loam texture, with less than 5% clay content, pH corrected to between 6 and 7, and an organic matter content of at least 2%. | 3 inch surface depth. |
Geotextile/Liner |
Use a non-woven geotextile fabric with a flow rate of > 110 gal./min./sq. ft. (e.g., Geotex 351 or equivalent) | Apply only to the sides and above the underdrain. For hotspots and certain karst sites only, use an appropriate liner on bottom. |
Choking Layer |
Lay a 2 to 4 inch layer of sand over a 2 inch layer of choker stone (typically #8 or #89 washed gravel), which is laid over the underdrain stone. | |
Stone Jacket
for Underdrain and/or Storage Layer |
1 inch stone should be double-washed and clean and free of all fines (e.g., VDOT #57 stone). | 12 inches for the underdrain; 12 to 18 inches for the stone storage layer, if needed |
Underdrains,
Cleanouts, and Observation Wells |
Use 6 inch rigid schedule 40 PVC pipe (or equivalent corrugated HDPE for micro-bioretention), with 3/8-inch perforations at 6 inches on center; position each underdrain on a 1% or 2% slope located nor more than 20 feet from the next pipe. | Lay the perforated pipe under the length of the bioretention cell, and install non-perforated pipe as needed to connect with the storm drain system. Install T's and Y's as needed, depending on the underdrain configuration. Extend cleanout pipes to the surface with vented caps at the Ts and Ys. |
Plant Materials |
Plant one tree per 250 square feet (15
feet on-center, minimum 1 inch caliper). Shrubs a minimum of 30 inches high planted a minimum of 10 feet on-center. Plant ground cover plugs at 12 to 18 inches on-center; Plant container-grown plants at 18 to 24 inches on-center, depending on the initial plant size and how large it will grow. |
Establish plant materials as specified
in the landscaping plan and the recommended plant list. In general, plant spacing must be sufficient to ensure the plant material achieves 80% cover in the proposed planting areas within a 3-year period. If seed mixes are used, they should be from a qualified supplier, should be appropriate for stormwater basin applications, and should consist of native species (unless the seeding is to establish maintained turf). |
SECTION 7: REGIONAL & SPECIAL CASE DESIGN ADAPTATIONS
7.1 Karst Terrain
Karst regions are found in much of the Ridge and Valley province of Virginia, which complicates both land development and stormwater design. While bioretention areas produce less deep ponding than conventional stormwater practices (e.g., ponds and wetlands), Level 2 bioretention designs (i.e., infiltration) are not recommended in any area with a moderate or high risk of sinkhole formation (Hyland, 2005). On the other hand, Level 1 designs that meet separation distance requirements (3 feet) and possess an impermeable bottom liner and an underdrain should work well. In general, micro-bioretention and bioretention basins with contributing drainage areas not exceeding 20,000 square feet are preferred (compared to bioretention with larger drainage areas), in order to prevent possible sinkhole formation. However, it may be advisable to increase standard setbacks to buildings.
7.2 Coastal Plain
The flat terrain, low hydraulic head, and high water table of many coastal plain sites can constrain the application of deeper bioretention areas (particularly Level 2 designs). In such settings, the following design adaptations may be helpful:
While these design criteria permit bioretention to be used on a wider range of coastal plain sites, it is important not to avoid using bioretention on marginal sites. Other stormwater practices, such as wet swales, ditch wetland restoration, and smaller linear wetlands, are often preferred alternatives for coastal plain sites.
7.3 Steep Terrain
In steep terrain, land with a slope of up to 15% may drain to a bioretention area, as long as a two cell design is used to dissipate erosive energy prior to filtering. The first cell, between the slope and the filter media, functions as a forebay to dissipate energy and settle any sediment that migrates down the slope. Designers may also want to terrace a series of bioretention cells to manage runoff across or down a slope. The drop in slope between cells should be limited to 1 foot and should be armored with river stone or a suitable equivalent.
7.4 Cold Climate and Winter Performance
Bioretention areas can be used for snow storage as long as an overflow is provided and they are planted with salt-tolerant, non-woody plant species. (NOTE: Designers may want to evaluate Chesapeake Bay wetland plant species that tolerate slightly brackish water.) Tree and shrub locations should not conflict with plowing and piling of snow into storage areas.
While several studies have shown that bioretention facilities operate effectively in Pennsylvania and West Virginia winters, it is a good idea to extend the filter bed and underdrain pipe below the frost line and/or oversize the underdrain by one pipe size to reduce the freezing potential.
7.5 Linear Highway Sites
Bioretention is a preferred practice for constrained highway right of ways when designed as a series of individual on-line or off-line cells. In these situations, the final design closely resembles that of dry swales. Salt tolerant species should be selected if salt compounds will be used to de-ice the contributing roadway in the winter.
SECTION 8: CONSTRUCTION
8.1. Construction Sequence
Construction Stage E&S Controls. Micro-bioretention and small-scale bioretention areas should be fully protected by silt fence or construction fencing, particularly if they will rely on infiltration (i.e., have no underdrains). Ideally, bioretention should remain outside the limit of disturbance during construction to prevent soil compaction by heavy equipment. Bioretention basin locations may be used as small sediment traps or basins during construction. However, these must be accompanied by notes and graphic details on the E&S plan specifying that (1) the maximum excavation depth at the construction stage must be at least 1 foot above the post-construction installation, and (2) the facility must contain an underdrain. The plan must also show the proper procedures for converting the temporary sediment control practice to a permanent bioretention facility, including dewatering, cleanout and stabilization.
8.2 Bioretention Installation
The following is a typical construction sequence to properly install a bioretention basin (also see Figure 9.16). The construction sequence for micro-bioretention is more simplified. These steps may be modified to reflect different bioretention applications or expected site conditions:
Step 1. Construction of the bioretention area may only begin after the entire contributing drainage area has been stabilized with vegetation. It may be necessary to block certain curb or other inlets while the bioretention area is being constructed. The proposed site should be checked for existing utilities prior to any excavation.
Step 2. The designer and the installer should have a preconstruction meeting, checking the boundaries of the contributing drainage area and the actual inlet elevations to ensure they conform to original design. Since other contractors may be responsible for constructing portions of the site, it is quite common to find subtle differences in site grading, drainage and paving elevations that can produce hydraulically important differences for the proposed bioretention area. The designer should clearly communicate, in writing, any project changes determined during the preconstruction meeting to the installer and the plan review/inspection authority.
Step 3. Temporary E&S controls are needed during construction of the bioretention area to divert stormwater away from the bioretention area until it is completed. Special protection measures such as erosion control fabrics may be needed to protect vulnerable side slopes from erosion during the construction process.
Step 4. Any pre-treatment cells should be excavated first and then sealed to trap sediments.
Step 5. Excavators or backhoes should work from the sides to excavate the bioretention area to its appropriate design depth and dimensions. Excavating equipment should have scoops with adequate reach so they do not have to sit inside the footprint of the bioretention area. Contractors should use a cell construction approach in larger bioretention basins, whereby the basin is split into 500 to 1,000 sq. ft. temporary cells with a 10-15 foot earth bridge in between, so that cells can be excavated from the side.
Step 6. It may be necessary to rip the bottom soils to a depth of 6 to 12 inches to promote greater infiltration.
Step 7. Place geotextile fabric on the sides of the bioretention area with a 6-inch overlap on the sides. If a stone storage layer will be used, place the appropriate depth of #57 stone on the bottom, install the perforated underdrain pipe, pack #57 stone to 3 inches above the underdrain pipe, and add approximately 3 inches of choker stone/pea gravel as a filter between the underdrain and the soil media layer. If no stone storage layer is used, start with 6 inches of #57 stone on the bottom, and proceed with the layering as described above.
Step 8. Deliver the soil media from an approved vendor, and store it on an adjacent impervious area or plastic sheeting. Apply the media in 12-inch lifts until the desired top elevation of the bioretention area is achieved. Wait a few days to check for settlement, and add additional media, as needed, to achieve the design elevation.
Step 9. Prepare planting holes for any trees and shrubs, install the vegetation, and water accordingly. Install any temporary irrigation.
Step 10. Place the surface cover in both cells (mulch, river stone or turf), depending on the design. If coir or jute matting will be used in lieu of mulch, the matting will need to be installed prior to planting (Step 9), and holes or slits will have to be cut in the matting to install the plants.
Step 11. Install the plant materials as shown in the landscaping plan, and water them during weeks of no rain for the first two months.
Step 12. Conduct the final construction inspection (see Section 9.2). Then log the GPS coordinates for each bioretention facility and submit them for entry into the local maintenance tracking database.

Figure 9.16. Typical Biofilter Construction Sequence
8.3 Construction Inspection
An example construction phase inspection checklist for Bioretention areas can be accessed at the CWP website at:
http://www.cwp.org/Resource_
SECTION 9: MAINTENANCE
9.1. Maintenance Agreements
Section 4 VAC
50-60-124 of the regulations specifies the circumstances under which
a maintenance agreement must be executed
between the owner and the local program. This section sets forth inspection
requirements, compliance procedures if maintenance is neglected, notification
of the local program upon transfer of ownership, and right-of-entry
for local program personnel.
For bioretention, maintenance agreements must contain recommended maintenance tasks and a copy of an annual inspection checklist. When micro-scale bioretention practices are applied on private residential lots, homeowners will need to be educated regarding their routine maintenance needs. A deed restriction, drainage easement or other mechanism enforceable by the qualifying local program must be in place to help ensure that rain gardens and bioretention filters are maintained and not converted or disturbed, as well as to pass the knowledge along to any subsequent owners. The mechanism should, if possible, grant authority for local agencies to access the property for inspection or corrective action.
9.2. First Year Maintenance Operations
Successful establishment of bioretention areas requires that the following tasks be undertaken in the first year following installation:
9.3. Maintenance Inspections
It is highly recommended that a spring maintenance inspection and cleanup be conducted at each bioretention area. The following is a list of some of the key maintenance problems to look for:
Example maintenance inspection checklists for Bioretention areas can be accessed in Appendix C of Chapter 9 of the Virginia Stormwater Management Handbook (2010) or at the Center for Watershed Protection website at:
http://www.cwp.org/Resource_
(scroll to Tool6:
Plan Review, BMP Construction, and Maintenance Checklists)
9.4. Routine and Non-Routine Maintenance Tasks
Maintenance of bioretention areas should be integrated into routine landscape maintenance tasks. If landscaping contractors will be expected to perform maintenance, their contracts should contain specifics on unique bioretention landscaping needs, such as maintaining elevation differences needed for ponding, proper mulching, sediment and trash removal, and limited use of fertilizers and pesticides. A customized maintenance schedule must be prepared for each bioretention facility, since the maintenance tasks will differ depending on the scale of bioretention, the landscaping template chosen, and the type of surface cover. A generalized summary of common maintenance tasks and their frequency is provided in Table 9.7.
The most common non-routine maintenance problem involves standing water. If water remains on the surface for more than 48 hours after a storm, adjustments to the grading may be needed or underdrain repairs may be needed. The surface of the filter bed should also be checked for accumulated sediment or a fine crust that builds up after the first several storm events. There are several methods that can be used to rehabilitate the filter (try the easiest things first, as listed below):
Table 9.7. Suggested Annual Maintenance Activities for Bioretention
|
Maintenance Tasks |
Frequency |
|
At least 4 times a year |
|
Twice during growing season |
|
As needed |
|
Annually |
|
Once every 2 to 3 years |
|
Every 3 years |
SECTION 9: REFERENCES
Lake County,
OH. Bioretention Guidance Manual. Available online at:
http://www2.lakecountyohio.
CWP. 2007. National Pollutant Removal Performance Database, Version 3.0. Center for Watershed Protection, Ellicott City, MD.
Schueler, T. 2008. Technical Support for the Baywide Runoff Reduction Method. Chesapeake Stormwater Network. Baltimore, MD. www.chesapeakestormwater.net
Prince George's Co., MD.
Bioretention Manual. Available online at:http://www.
Maryland Department
of the Environment. 2001. Maryland Stormwater Design Manual.
http://www.mde.state.md.us/
Wisconsin Department
of Natural Resources. Stormwater Management Technical Standards.
http://www.dnr.state.wi.us/
Hirschman, D., L. Woodworth and S. Drescher. 2009. Technical Report: Stormwater BMPs in Virginia's James River Basin - An Assessment of Field Conditions and Programs. Center for Watershed Protection. Ellicott City, MD.
Hunt, W.F. III and W.G. Lord. 2006. "Bioretention Performance, Design, Construction, and Maintenance." North Carolina Cooperative Extension Service Bulletin. Urban Waterways Series. AG-588-5. North Carolina State University. Raleigh, NC.
Hyland, S. 2005. "Analysis of sinkhole susceptibility and karst distribution in the Northern Shenandoah Valley (Virginia): impacts for LID site suitability models." M.S. Thesis. Virginia Polytechnic Institute and State University. Blacksburg, VA.
Minnesota Stormwater Steering Committee (MSSC). 2005. The Minnesota Stormwater Manual.
Schueler et al. 2007. Urban Stormwater Retrofit Practices. Manual 3 in the Urban Subwatershed Restoration Manual Series. Center for Watershed Protection. Ellicott City, MD.
North Shore City. 2007. Bioretention Design Guidelines. Sinclair, Knight and Merz. Auckland, New Zealand.
In addition, the following individuals provided review and input for this version of the specification. Rick Scafidi (EQR), Bill Hunt (NCSU), Scott Thomas (JCC), Dave Hirschman (CWP) Don Rissmeyer (VA ASCE), Randy Greer (DENRC), Doug Biesch (WEG), Stuart Stein (GKY), Tim Schueler (MC), Christie Minami (MD SHA). Special thanks to the staff at WEG for providing the design schematics and details.
APPENDIX
9-A
URBAN BIORETENTION
Stormwater
Planters
Expanded
Tree Pits
Stormwater
Curb Extensions
VERSION
1.7
March 8,
2010
![]() |
![]() |
![]() |
SECTION 9-A-1: DESCRIPTION
Urban bioretention practices are similar in function to regular bioretention practices except they are adapted to fit into "containers" within urban landscapes. Typically, urban bioretention is installed within an urban streetscape or city street right-of-way, urban landscaping beds, tree pits and plazas, or other features within an Urban Development Area. Urban bioretention is not intended for large commercial areas, nor should it be used to treat small sub-areas of a large drainage area such as a parking lot. Rather, urban bioretention is intended to be incorporated into small fragmented drainage areas such as shopping or pedestrian plazas within a larger urban development.
Urban bioretention features hard edges, often with vertical concrete sides, as contrasted with the more gentle earthen slopes of regular bioretention. These practices may be open-bottomed, to allow some infiltration of runoff into the sub-grade, but they generally are served by an underdrain.
Stormwater planters (also known as vegetative box filters or foundation planters) take advantage of limited space available for stormwater treatment by placing a soil filter in a container located above ground or at grade in landscaping areas between buildings and roadways (Figure 9-A.1). The small footprint of foundation planters is typically contained in a precast or cast-in-place concrete vault. Other materials may include molded polypropylene cells and precast modular block systems.

Figure 9-A.1. Stormwater Planters
Extended tree pits are installed in the sidewalk zone near the street where urban street trees are normally installed. The soil volume for the tree pit is increased and used as a stormwater (Figure 9-A.2). Treatment is increased by using a series of connected tree planting areas together in a row. The surface of the enlarged planting area may be mulch, grates, permeable pavers, or conventional pavement. The large and shared rooting space and a reliable water supply increase the growth and survival rates in this otherwise harsh planting environment.

Figure 9-A.2. Expanded Tree Pits
Stormwater curb extensions (also known as parallel bioretention) are installed in the road right-of way either in the sidewalk area or in the road itself. In many cases, curb extensions serve as a traffic calming or street parking control device. The basic design adaptation is to move the raised concrete curb closer to the street or in the street, and then create inlets or curb cuts that divert street runoff into depressed vegetated areas within the expanded right of way (Figure 9-A.3).
Figure 9-A.3. Stormwater Curb Extensions
Each urban bioretention variant is planted with a mix of trees, shrubs, and grasses as appropriate for its size and landscaping context.
SECTION 9-A-2: PERFORMANCE
The typical stormwater functions of an urban bioretention area are described in Table 9-A.1. The three major design variants of urban bioretention are described below:
Table 9-A.1. Summary of Stormwater Functions Provided by Urban Bioretention Areas
|
Stormwater Function |
Level 1 Design |
Level 2 Design |
| Annual Runoff Reduction (RR) | 40% (for Water Quality credit in the RRM spreadsheet only) 0% credit for Channel Protection |
NA |
| Total Phosphorus (TP) Removal 1 | 25% |
NA |
| Total Nitrogen (TN) Removal 1 | 40% |
NA |
| Channel Protection | None; or if sized according to Bioretention Basin, follow the Level 1 Bioretention basin criteria. | |
| Flood Mitigation | None | |
| 1 Change in the event mean concentration (EMC) through the practice. The actual nutrient mass load removed is the product of the removal rate and the runoff reduction rate (see Table 1 in the Introduction to the New Virginia Stormwater Design Specifications). | ||
SECTION 9-A-3: DESIGN TABLE
Table 9-A.2. Urban Bioretention Design Criteria
|
Level 1 Design
Only (RR: 40; TP: 25 ) |
Sizing (Refer to
Section 9-A-6.1):
Surface Area (sq. ft.) = Tv/2 = {[(1.0 inch)(Rv)(A)/12)] - the volume reduced by an upstream BMP}/2 |
Underdrain =
Schedule 40 PVC with clean-outs
(Refer to the Main Bioretention Design Specification, Section 9.8) |
Maximum Drainage Area
= 2,500 sq. ft. |
Maximum Ponding Depth
= 6 to 12 inches 1 |
Filter media depth
minimum = 30 inches; recommended maximum = 48 inches |
Media and Surface Cover
(Refer to the Main Bioretention Design Specification,
Section 9.8) |
Sub-soil testing (Refer
to the Main Bioretention Design Specification,
Section 9.8) |
Inflow = sheetflow,
curb cuts, trench drains, roof drains, concentrated flow, or equivalent |
Building setbacks (Refer
to Section 9-A-5) |
Deeded maintenance
O&M plan (Refer to the Main Bioretention Design Specification,
Section 9.1) |
| 1 Ponding depth above 6 inches will require
a specific planting plan to ensure appropriate plants (Refer to the Main Bioretention Design Specification, Section 6.8). |
SECTION 9-A-4: TYPICAL DETAILS

Figure
9-A.4. Stormwater Planter Cross-Section

Figure 9-A.5. Expanded Tree Pit Details
Portland, Oregon
(Portland BES, 2004) has thorough construction details for stormwater
curb extensions, expanded tree pits, and utility house connections,
available online at http://www.portlandonline.com/
SECTION 9-A-5: PHYSICAL FEASIBILITY & DESIGN APPLICATIONS
In general, urban bioretention has the same constraints as regular bioretention, along with a few additional constraints as noted below:
Contributing Drainage Area. Urban bioretention is classified as a micro-bioretention practice and is therefore limited to 2,500 sq. ft. of drainage area to each unit. However, this is considered a general rule; larger drainage areas may be allowed with sufficient flow controls and other mechanisms to ensure proper function, safety, and community acceptance. The drainage areas in these urban settings are typically considered to be 100% impervious. While multiple units can be installed to maximize the treatment area in ultra-urban watersheds, urban bioretention is not intended to be used as treatment for large impervious areas (such as parking lots).
Adequate Drainage. Urban bioretention practice elevations must allow the untreated stormwater runoff to be discharged at the surface of the filter bed and ultimately connect to the local storm drain system.
Available Hydraulic Head. In general, 3 to 5 feet of elevation difference is needed between the downstream storm drain invert and the inflow point of the urban bioretention practice. This is generally not a constraint, due to the standard depth of most storm drains systems.
Setbacks
from Buildings . If an impermeable liner
and an underdrain are used, no setback is needed from the building.
Otherwise, the standard 10 foot down-gradient setback applies.Roads
Proximity to Underground Utilities. Urban bioretention practices frequently compete for space with a variety of utilities. Since they are often located parallel to the road right-of-way, care should be taken to provide utility-specific horizontal and vertical setbacks. However, conflicts with water and sewer laterals (e.g., house connections) may be unavoidable, and the construction sequence must be altered, as necessary, to avoid impacts to existing service.
Overhead Wires. Designers should also check whether future tree canopy heights achieved in conjunction with urban bioretention practices will interfere with existing overhead telephone, cable communications and power lines.
Minimizing
External Impacts. Because urban bioretention practices are installed
in highly urban settings, individual units
may be subject to higher public visibility, greater trash loads, pedestrian traffic, vandalism, and even vehicular loads. Designers
should design these practices in ways that prevent, or at least minimize,
such impacts. In addition, designers should clearly recognize the need
to perform frequent landscaping maintenance to remove trash, check for
clogging, and maintain vigorous vegetation. The urban landscape context
may feature naturalized landscaping or a more formal deign. When urban
bioretention is used in sidewalk areas of high foot traffic, designers
should not impede pedestrian movement or create a safety hazard. Designers
may also install low fences, grates or other measures to prevent damage
from pedestrian short-cutting across the practices.
SECTION 9-A-6: DESIGN CRITERIA
Urban bioretention practices are similar in function to regular bioretention practices except they are adapted to fit into "containers" within urban landscapes. Therefore, special sizing accommodations are made to allow these practices to fit in very constrained areas where other surface practices may not be feasible.
6.1. Sizing of Urban Bioretention
The required surface area of the urban bioretention filter is one-half of the Treatment Volume (Equation 9-A.1 below). This criterion represents a balance between the need to size these structures so as to provide a reasonable alternative in ultra urban settings and the relationship between the surface area size, media permeability, and drawdown requirements. Ideally, urban bioretention facilities are in close proximity to the public or users of the adjacent buildings and/or commercial areas, and thus subjected to increased scrutiny. This provides a theoretical basis for adjusting the clogging factor for the media permeability coefficient (k, ft/day), or an increase in the allowable maximum drawdown time, resulting in the smaller sizing. However, as a result, Level 1 urban bioretention will only count towards water quality credit through the 40% volume reduction and/or the 25% TP pollutant removal. There is no credit given to channel protection due to the reduced surface area and storage volume.
Equation 9-A.1. Urban Bioretention Sizing
SA (sq. ft.) = Tv (cu. ft.) / 2.0 ft.
Where:
SA = the surface area of
the urban bioretention facility (in square feet)
Tv = the required Treatment Volume
(in cubic feet)
6.2 General Design Criteria for Urban Bioretention
Design of urban bioretention should follow the general guidance presented in the main part of this Bioretention design specification. The actual geometric design of urban bioretention is usually dictated by other landscape elements such as buildings, sidewalk widths, utility corridors, retaining walls, etc. Designers can divert fractions of the runoff volume from small impervious surfaces into micro-bioretention units that are integrated with the overall landscape design. Inlets and outlets should be located as far apart as possible. The following is additional design guidance that applies to all variations of urban bioretention:
6.3 Specific Design Issues for Stormwater Planters
Since stormwater planters are often located near building foundations, waterproofing by using a watertight concrete shell or an impermeable liner is required to prevent seepage.
6.4 Specific Design Issues for Expanded Tree Pits
6.5 Specific Design Issues for Stormwater Curb Extensions
Roadway stability can be a design issue where stormwater curb extensions are installed. Consult design standards pertaining to roadway drainage. It may be necessary to provide a barrier to keep water from saturating the road's sub-base and demonstrate it is capable of supporting H-20 axel loads.
6.6 Planting and Landscaping Considerations
The degree of landscape maintenance that can be provided will determine some of the planting choices for urban bioretention areas. The planting cells can be formal gardens or naturalized landscapes.
In areas where less maintenance will be provided and where trash accumulation in shrubbery or herbaceous plants is a concern, consider a "turf and trees" landscaping model. Spaces for herbaceous flowering plants can be included. This may be attractive at a community entrance location.
Native trees or shrubs are preferred for urban bioretention areas, although some ornamental species may be used. As with regular bioretention, the selected perennials, shrubs, and trees must be tolerant of salt, drought, and inundation. Additionally, tree species should be those that are known to survive well in the compacted soils and polluted air and water of an urban landscape.
SECTION 9-A-7: URBAN BIORETENTION MATERIAL SPECIFICATIONS
Please consult the main part of this design specification (Table 9.6) for the typical materials needed for filter media, stone, mulch and other bioretention features. The unique components for urban bioretention may include the inlet control device, a concrete box or other containing shell, protective grates, and an underdrain that daylights to another stormwater practice or connects to the storm drain system. The underdrain should:
SECTION 9-A.8: CONSTRUCTION
The construction sequence and inspection requirements for urban bioretention are generally the same as micro-bioretention practices. Consult the construction sequence and inspection guidance provided in the main part of this design specification. In cases where urban bioretention is constructed in the road or right-of-way, the construction sequence may need to be adjusted to account for traffic control, pedestrian access and utility notification.
Urban bioretention areas should only be constructed after the drainage area to the facility is completely stabilized. The specified growth media should be placed and spread by hand with minimal compaction, in order to avoid compaction and maintain the porosity of the media. The media should be placed in 8 to 12 inch lifts with no machinery allowed directly on the media during or after construction. The media should be overfilled above the proposed surface elevation, as needed, to allow for natural settling. Lifts may be lightly watered to encourage settling. After the final lift is placed, the media should be raked (to level it), saturated, and allowed to settle for at least one week prior to installation of plant materials.
SECTION 9-A-9: MAINTENANCE
Routine operation and maintenance are essential to gain public acceptance of highly visible urban bioretention areas. Weeding, pruning, and trash removal should be done as needed to maintain the aesthetics necessary for community acceptance. During drought conditions, it may be necessary to water the plants, as would be necessary for any landscaped area.
To ensure proper performance, inspectors should check that stormwater infiltrates properly into the soil within 24 hours after a storm. If excessive surface ponding is observed, corrective measures include inspection for soil compaction and underdrain clogging. Consult the maintenance guidance outlined in the main part of this design specification.
SECTION 9-A-10: DESIGN REFERENCES
Center for
Watershed Protection. 2006. Urban Watershed Forestry Manual. Part 2: Conserving and Planting
Trees at Development Sites.
Ellicott City, MD. Available online at: http://www.cwp.org/forestry/
City of Portland.
Bureau of Environmental Services. (Portland BES). 2004. Portland
Stormwater Management Manual. Portland, OR. http://www.portlandonline.com/
Credit Valley Conservation. 2008. Credit River Stormwater Management Manual. Mississauga, Ontario.
Northern Virginia Regional Commission. 2007. Low Impact Development Supplement to the Northern Virginia BMP Handbook. Fairfax, Virginia
Saxton, K.E., W.J. Rawls, J.S. Romberger, and R.I. Papendick. 1986. "Estimating generalized soil-water characteristics from texture." Soil Sci. Soc. Am. J. 50(4):1031-1036.
Schueler, T.,
D. Hirschman, M. Novotney and J. Zielinski. 2007. Urban stormwater
retrofit practices. Manual 3 in the Urban Subwatershed Restoration
Manual Series. Center for Watershed Protection, Ellicott City, MD.
APPENDIX 9-B
ADDITIONAL
DETAILS AND SCHEMATICS
FOR REGULAR
BIORETENTION PRACTICES
VERSION 1.6
September
31, 2009

Figure 9-B.1.
4" P.V.C. Cleanout Detail

Figure 9-B.2. Typical
Biofilter Planting Specifications

Figure 9-B.3. Typical Bioretention Basin Berm
Figure 9-B.4. Typical Bioretention Basin - Inflow & Outflow - Section